F.H. Bertling Logistics Malaysia successfully completed the transportation of 182 concrete coated linepipes from Kuantan Port to Kota Kinabalu Port.
The cargo consisted of 12-metre-long concrete coated linepipes with a total shipment volume of 1,224 MT and 866 CBM. The heaviest unit weighed approximately 9 MT.
POL: Kuantan, Malaysia
POD: City, Malaysia
Volume: 1,224 MT and 866 CBM
Bertling Team: Malaysia
F.H. Bertling Logistics managed the full project logistics scope, including vessel chartering on a FILO basis, customs clearance, cargo dunnage and securing, MWS coordination, on-site supervision, and unloading operations at the destination port.
The project required close operational coordination to ensure the safe handling and transport of oversized cargo units throughout all stages of the shipment. With dedicated supervision at Kuantan Port and careful planning between all stakeholders, the shipment was transported safely and efficiently within the scheduled timeline.