Services

Support

KTL Switchgear Upgrade at Tengiz Oil Field – Substation Module Transportation Project

Bertling Atyrau successfully delivered the KTL Switchgear Upgrade (KSU) Project at the Tengiz Oil Field, executing complex heavy-lift and project logistics operations under live plant SIMOPS conditions.
The project involved the transportation and installation of oversized substation modules and HVAC platforms, including the critical requirement to maintain continuous HVAC operation throughout transport and laydown.

Despite long distances, challenging weather, and strict safety requirements within an operating oil field, the project was completed safely, on schedule, and with zero incidents.

POL: PSI Almaty, Kazakhstan
POD: Tengiz Oil Field, Atyrau Oblast, Kazakhstan
Industry: Oil & Gas / Energy Infrastructure
Volume: 16 units including 12 substation modules (up to 92,000 kg each) and 4 HVAC platforms (approx. 8,630 kg each), transported in 4 convoys.
Bertling Team: Bertling Atyrau – Project Logistics & Heavy-Lift Team
(in cooperation with TCO, ALE and WoodKSS)

We would like to sincerely thank all project partners for their strong collaboration, professionalism, and commitment throughout the project. The successful execution of the KTL Switchgear Upgrade Project under live plant SIMOPS conditions - with zero safety incidents - stands as a clear example of what can be achieved through early planning, strong teamwork, and shared dedication to excellence in heavy-lift and project logistics.

How can we support you?

Heavy-Lift Services          How we work          Contact us