Bertling Indonesia has just completed a complex movement of a 750HP land rig from a staging area to the drilling site in Indonesia.
The move consisted of a volume of over 4,000cbm of 105 packages. The works consisted of supplying cranes, forklifts, and suitable trailers to shift to the well location while the dismantling was ongoing.
Volume: 4,000 cbm
Heaviest piece: Main Truck Rig Carrier, weighing 58 tonnes and measuring 16.5m (L) x 3.4m (W) x 3.5m (H)
Detailed preparation and coordination were managed to ensure the rig was delivered on time, despite over a three-week period of wet weather.
A great achievement by the Bertling Indonesia team and another example of our ability to handle complex project logistics operations safely and efficiently.